Fortescue: Jan-Mar Pilbara iron ore output will be lower than guidance

Friday, 25 March 2011 14:07:48 (GMT+3)   |  
Australian iron ore miner Fortescue Metals Group has said that heavy rainfall across the Pilbara region in Western Australia has impacted its mining operations and so its iron ore production for the March quarter this year will be at the bottom end or slightly below its previous guidance of 8.5-9 million mt.
 
The combination of lower production impacted by weather and the commissioning of Fortescue's second major ore processing facility at Christmas Creek will result in higher cash operating costs on a per unit basis for the March quarter 2011, reads the company's statement.
 
Fortescue also said that its operations are now running as per normal and commissioning of the new Christmas Creek ore processing facility is underway, with a ramp-up to 55 million mt per year expected during the June quarter 2011 as planned.

Similar articles

Iron ore in China edges down gradually this week amid slow consumption

19 Jun | Scrap & Raw Materials

Major steel and raw material futures prices in China – June 19, 2025 

19 Jun | Longs and Billet

India’s JSW Steel and Andhra Pradesh government ink pact to construct iron ore beneficiation plant

19 Jun | Steel News

Daily iron ore prices CFR China - June 18, 2025

18 Jun | Scrap & Raw Materials

Major steel and raw material futures prices in China – June 18, 2025 

18 Jun | Longs and Billet

Ex-Brazil high-grade iron ore prices decline from last week

17 Jun | Scrap & Raw Materials

Daily iron ore prices CFR China - June 17, 2025

17 Jun | Scrap & Raw Materials

Metso to supply key process equipment to China’s Jinan iron ore concentrator plant to be built in Oman

17 Jun | Steel News

Australian consortium secures funding for ambitious low-carbon ironmaking project

17 Jun | Steel News

Major steel and raw material futures prices in China – June 17, 2025 

17 Jun | Longs and Billet